CAPITAL INVESTMENTS | WATER
View Drive Booster Pump Upgrades
DESCRIPTION
PROJECT ID: | W 21.0 |
ESTIMATED COST: | $750,000 |
ACTUAL COST: | TBD |
- Reconstructs the pump station in an aboveground structure to provide sufficient room for operation and maintenance.
- Pumps will be resized to meet future demands for service in the area and may require property acquisition.
- Includes new pumps, valves, control, and electrical systems.
WHY IT’S NEEDED
The current booster pump is undersized and obsolete. A replacement station would expand to meet growth projections. The booster pump is a backup for Well No. 6 and serves industrial areas as well as the Eastern Oregon Higher Education Center, Walmart Distribution Center, Pioneer Seed, and the Eastern Oregon Trade and Event Center.
PROJECT STATUS:
Planned
PROJECT MILESTONES
Scheduled for
2025-2026
LAST UPDATED: 02/18/21