CAPITAL INVESTMENTS | STREETS
E. Penney Ave. (SE Kelli Blvd. to Highway 395)
E. Penney Ave.
DESCRIPTION
PROJECT ID: | ST 22.0 |
ESTIMATED COST: | $995,000* |
ACTUAL COST: | $1,224,980.54** |
- Extends approximately 800 feet of roadway in the South Hermiston Industrial Park between SE Kelli Boulevard and U.S. Highway 395
- Includes curb, gutter, and sidewalk on the south side
- Pedestrian ramps will meet current ADA standards
* funded by grants
**Right of way acquisition costs caused the project to exceed original estimate
WHY IT’S NEEDED
E. Penney Avenue needs to be extended to eventually develop a secondary east/west route in the South Hermiston Industrial Park. This project will continue to spur growth in this area with additional connectivity.
PROJECT STATUS:
Complete
PROJECT MILESTONES
November 2022
Final Right of Way acquisition completed.
December 2022
Final roadway design begins.
February 2023
Project advertised.
July 2023
Contractor completed paving in July and reopened to traffic.
LAST UPDATED: 12/20/23