CAPITAL INVESTMENTS | STREETS

Geer/Harper/1st Realignment

The intersecion of N.W. Geer Road, W. Harper Ave. and N. 1st Place.

DESCRIPTION

PROJECT ID: ST 4.0
ESTIMATED COST: $1,500,000
ACTUAL COST: TBD
  • Will redevelop the three-way intersection that also includes Union Pacific railway.
  • Road work will include resurfacing for a smoother surface, restored drainage, and matching sidewalk elevations, with work coordinated with Union Pacific and other utilities.
  • Stripes, crosswalks and manholes will also be adjusted.

WHY IT’S NEEDED

The intersection needs to be reconstructed to improve traffic and pedestrian access, and ensure connectivity to property east of N. 1st Place. The current configuration makes access difficult for large trucks, and traffic backs up on Harper Road during busy times of day.

Repair work will also eliminate extensive patching and depressed areas from traffic and development. Sidewalks will be added.

PROJECT STATUS:
In Progress
PROJECT MILESTONES

April 2020

Acquired right of way for project.

May 2020

Design engineering begins.

June 2020

Contract executed with  Union Pacific Railroad for rail crossing design and review.

Fall 2020

Union Pacific review requires realignment to avoid rail siding.

March 2021

Union Pacific confirms new alignment is allowable without closing three other crossings

Scheduled for
2021-2022

“Hermiston sets sights on redesign of Harper Road-Geer Road intersection” – Northeast Oregon Now, 1/28/20 (link)

“Confusing intersection added to Hermiston transportation priority list” – East Oregonian, 6/11/14 (link)

May 2021

Additional right of way acquisition begins

LAST UPDATED: 01/18/23