CAPITAL INVESTMENTS | Wastewater
Lift Station No. 1 Pump Upgrades
Lift Station No. 1.
DESCRIPTION
PROJECT ID: | S 6.0 |
ESTIMATED COST: | $100,000 |
ACTUAL COST: | $97,000 |
- Will replace pump column, lineshaft, pump bowls and impellers for each of the three pumps in the wetwell.
- Pump motors have already been replaced, and will be mounted to the new equipment and sewage bypass pumping.
WHY IT’S NEEDED
The three line shaft pumps were originally installed in 1981 and reaching the end of their design life. Replacement will avoid lift station problems.
PROJECT STATUS:
Complete
PROJECT MILESTONES
July 2020
Work has begun on this project, but due to Covid-19, sourcing qualified contractors has been a challenge. Work will continue in to Fiscal Year 2020-21.
LAST UPDATED: 01/19/23