CAPITAL INVESTMENTS | Wastewater

Lift Station No. 1 Pump Upgrades

Lift Station No. 1.

DESCRIPTION

PROJECT ID: S 6.0
ESTIMATED COST: $100,000
ACTUAL COST: $97,000
  • Will replace pump column, lineshaft, pump bowls and impellers for each of the three pumps in the wetwell.
  • Pump motors have already been replaced, and will be mounted to the new equipment and sewage bypass pumping.

WHY IT’S NEEDED

The three line shaft pumps were originally installed in 1981 and reaching the end of their design life. Replacement will avoid lift station problems.

PROJECT STATUS:
Complete
PROJECT MILESTONES

July 2020

Work has begun on this project, but due to Covid-19, sourcing qualified contractors has been a challenge.  Work will continue in to Fiscal Year 2020-21.

LAST UPDATED: 01/19/23