Lift Station No. 1.

DESCRIPTION

PROJECT ID: S 6.0
ESTIMATED COST: $100,000
ACTUAL COST: TBD
  • Will replace pump column, lineshaft, pump bowls and impellers for each of the three pumps in the wetwell.
  • Pump motors have already been replaced, and will be mounted to the new equipment and sewage bypass pumping.

WHY IT’S NEEDED

The three line shaft pumps were originally installed in 1981 and reaching the end of their design life. Replacement will avoid lift station problems.

PROJECT STATUS:
Planned
PROJECT MILESTONES

Schedule for 2019-2020

LAST UPDATED: 01/28/20