CAPITAL INVESTMENTS | Wastewater

S.E. 7th Street Line Replacement (Phase I)

S.E. 7th Street in Hermiston.

DESCRIPTION

PROJECT ID: S 2.0
ESTIMATED COST: $160,000
ACTUAL COST: $136,000
  • Replaces 650 feet of sewer line under S.E. 7th Street between E. Main and E. Newport
  • Installs new polyvinyl chloride pipe and precast manholes
  • Included roadway restoration, traffic control upgrades, and sewage bypass pumping to improve collection system.

WHY IT’S NEEDED

The existing sewer line lacks the capacity to provide expanding service to the Eastern Oregon Trade and Event Center and Cook Industrial Area. The replacement will allow continued development in the area.

PROJECT STATUS:
Complete
PROJECT MILESTONES

Completed in July 2019

LAST UPDATED: 02/06/20