CAPITAL INVESTMENTS | STREETS

Stormwater Lift Station No. 2 – Alarms

Stormwater Lift Station No. 2.

DESCRIPTION

PROJECT ID: ST 19.0
ESTIMATED COST: $80,000*
ACTUAL COST: TBD
  • Upgrades electrical and control systems, including engineering services.

* Plus inflation depending on year constructed

WHY IT’S NEEDED

The alarms on this older pump station are not working as needed, which poses a risk of overflow which could create traffic hazards.

PROJECT STATUS:
Potential
PROJECT MILESTONES

Not yet scheduled

LAST UPDATED: 03/25/21