CAPITAL INVESTMENTS | Wastewater
Treatment Plant Admin Building HVAC Upgrades
Recycled water treatment plant administrative building’s heating, ventilation and air conditioning system.
DESCRIPTION
PROJECT ID: | S 17.0 |
ESTIMATED COST: | $40,000 |
ACTUAL COST: | $53,974.62* |
- Installs new heat pump, furnace and ducting for a new heating, ventilation and air conditioning system
- Building and electrical system modifications may be required
WHY IT’S NEEDED
Laboratory test procedures and compliance regulations are continuously increasing. A new air conditioning system is needed to obtain and maintain certified compliance with existing and anticipated regulations.
*Included additional insulation work
PROJECT STATUS:
Complete
PROJECT MILESTONES
Completed in July 2019
LAST UPDATED: 01/31/20