CAPITAL INVESTMENTS | Wastewater

Treatment Plant Admin Building HVAC Upgrades

Recycled water treatment plant administrative building’s heating, ventilation and air conditioning system.

DESCRIPTION

PROJECT ID: S 17.0
ESTIMATED COST: $40,000
ACTUAL COST: $53,974.62*
  • Installs new heat pump, furnace and ducting for a new heating, ventilation and air conditioning system
  • Building and electrical system modifications may be required

WHY IT’S NEEDED

Laboratory test procedures and compliance regulations are continuously increasing. A new air conditioning system is needed to obtain and maintain certified compliance with existing and anticipated regulations.

*Included additional insulation work

PROJECT STATUS:
Complete
PROJECT MILESTONES

Completed in July 2019

LAST UPDATED: 01/31/20

© Copyright - City of Hermiston