CAPITAL INVESTMENTS | WATER

Well No. 6, Reservoir No. 2 Exterior Painting

DESCRIPTION

PROJECT ID: W 24.0
ESTIMATED COST: $115,000*
ACTUAL COST: TBD
  • Project includes sandblasting, priming, and painting all exterior surfaces.
  • May require draining reservoir to ensure proper paint curing.

*plus inflation depending on year constructed

WHY IT’S NEEDED

Repainting is needed to minimize further corrosion of the steel plates. The reservoir was last painted in 1996. A change in color is also recommended to prevent pheasants from flying into the reservoir.

PROJECT STATUS:
Potential
PROJECT MILESTONES

Scheduled for 2026-27.

LAST UPDATED: 01/18/23