CAPITAL INVESTMENTS | Wastewater

McDonald’s/Highway 395 Sewer Line Replacement

The S.E. Street gravity sewer line.

DESCRIPTION

PROJECT ID: S 12.0
ESTIMATED COST: $330,000
ACTUAL COST: $180,004.54*
  • Replaces existing sanitary sewer lines in poor condition or with capacity limitations
  • Installs about 700 feet of new polyvinyl chloride sewer pipe north of McDonald’s
  • Includes roadway restoration, traffic control, high groundwater mitigation, and sewage bypass pumping

* The cost coming in below estimate is attributable to a very low bid by the construction contractor, which, with direct oversight by Anderson Perry, was delivered satisfactorily with minimal change-orders.

WHY IT’S NEEDED

Pipe segments were found to have structural failures in multiple locations and failing joints, causing pipe blockage and requires monthly cleaning. Additionally, pipe failure may be allowing sewage to exfiltrate into the surrounding soil. New sewer lines would eliminate current monthly maintenance costs and provide watertight lines to protect existing groundwater resources from contamination.

PROJECT STATUS:
Complete
PROJECT MILESTONES

July 2021

Design work begins.

February 2022

90% design complete, including new routing to avoid traffic disruption/boring in US395.

March 2022

Easement acquisition process begins for alternative route.

November 2022

Council approves easement resolution to move forward with construction. Bid documents in development.

August 2023

Sewer blockage requires emergency repair to section under Walmart driveway.

December 2023

Project advertised for bids.

January 2024

Contract Awarded to Odessey Contracting for $105,170.

February 2024

Contractor begins project.

May 2024

Contractor concludes project.

LAST UPDATED: 06/07/24