CAPITAL INVESTMENTS | Wastewater

Lift Station No. 3 Upgrades

Lift Station No. 3 is underneath Highway 395.

DESCRIPTION

PROJECT ID: S 15.0
ESTIMATED COST: $450,000
ACTUAL COST: $1,407,783.49*
  • Extends a gravity line to Lift Station No. 6, which is also in poor shape (see W 13.0). Extending the line under Union Pacific Railroad tracks is more cost effective than replacing both lift stations
  • Traffic control will be necessary

* Challenges encountered with boring under the railroad required demobilization and a significant change in the equipment necessary to complete the job, which led to significant cost increases from the original estimate.

WHY IT’S NEEDED

Lift Station No. 3 was built in approximately 1981 and located underneath Highway 395. The pump and electrical systems need to be replaced.

PROJECT STATUS:
Complete
PROJECT MILESTONES

Spring 2020

Preliminary engineering concludes decommissioning Lift #3 and installing new gravity lines to be feasible and more cost effective than upgrading and replacing Lift #3.

July 2020

Design Engineering begins for new project.

Fall 2020

Preliminary Engineering completed and submitted to Union Pacific Railroad for review of boring under tracks.

Spring 2021

Review continues by Union Pacific Railroad.

August 2021

Union Pacific Railroad review complete. Bid documents prepared for project advertisement.

March 2022

Contract awarded to Tapani, Inc. for $561,924. (Staff report)

April 2022

Railroad boring and trenching begins.

May 2022

Boring contractor struck a metal obstruction believed to be a railcar, requiring a pause in the project to dig a larger casing to cut through the obstruction. This is estimated to increase the cost to $1.2 million.

November 2022

Boring completed underneath railroad line is complete.

December 2022

Project winterized, scheduled to resume in the spring.

February 2023

Work begins to extend sewer main in Ridgeway Right of Way from the rail line with some minor work in Highway 395 ahead of planned decommissioning in March.

June 2023

Contractor completes all items and system fully placed in service.

LAST UPDATED: 12/20/23