CAPITAL INVESTMENTS | Wastewater
Lift Station No. 3 Upgrades
Lift Station No. 3 is underneath Highway 395.
DESCRIPTION
PROJECT ID: | S 15.0 |
ESTIMATED COST: | $450,000 |
ACTUAL COST: | $1,407,783.49* |
- Extends a gravity line to Lift Station No. 6, which is also in poor shape (see W 13.0). Extending the line under Union Pacific Railroad tracks is more cost effective than replacing both lift stations
- Traffic control will be necessary
* Challenges encountered with boring under the railroad required demobilization and a significant change in the equipment necessary to complete the job, which led to significant cost increases from the original estimate.
WHY IT’S NEEDED
Lift Station No. 3 was built in approximately 1981 and located underneath Highway 395. The pump and electrical systems need to be replaced.
PROJECT STATUS:
Complete
PROJECT MILESTONES
Spring 2020
Preliminary engineering concludes decommissioning Lift #3 and installing new gravity lines to be feasible and more cost effective than upgrading and replacing Lift #3.
July 2020
Design Engineering begins for new project.
Fall 2020
Preliminary Engineering completed and submitted to Union Pacific Railroad for review of boring under tracks.
Spring 2021
Review continues by Union Pacific Railroad.
August 2021
Union Pacific Railroad review complete. Bid documents prepared for project advertisement.
March 2022
Contract awarded to Tapani, Inc. for $561,924. (Staff report)
April 2022
Railroad boring and trenching begins.
May 2022
Boring contractor struck a metal obstruction believed to be a railcar, requiring a pause in the project to dig a larger casing to cut through the obstruction. This is estimated to increase the cost to $1.2 million.
November 2022
Boring completed underneath railroad line is complete.
December 2022
Project winterized, scheduled to resume in the spring.
February 2023
Work begins to extend sewer main in Ridgeway Right of Way from the rail line with some minor work in Highway 395 ahead of planned decommissioning in March.
June 2023
Contractor completes all items and system fully placed in service.
LAST UPDATED: 12/20/23