CAPITAL INVESTMENTS | Wastewater
Lift Station No. 4 Reconstruction
Lift Station No. 4.
DESCRIPTION
| PROJECT ID: | S 11.0 |
| ESTIMATED COST: | $600,000 |
| ACTUAL COST: | $858,527.37* |
- Includes well structure, pumps, ventilation system, internal piping, and electrical control system upgrades
- Design will need to be analyzed during design and may require additional property for new pump chamber
- Odor control system will need to be included
* Actual cost affected by inflation on electrical and control components and expansion for street resurfacing and reconstruction from the original project scope.
WHY IT’S NEEDED
Lift Station No. 4 was built in 1981 and the submersible duplex pump station has experienced corrosion on both metal and brick. Replacement of the wetwell will increase capacity, eliminate porous brick, and safeguard the environment. Ventilation of the structure is poor and electrical systems are nearing the end of their expected lives.
PROJECT STATUS:
Complete
PROJECT MILESTONES
December 2024
All systems functional and operating, and streets re-opened. Project substantially complete and punchlist begins.
August 2024
Traffic Control Plan approved (see plan), construction slated to begin.
May 2024
Bids Opened
April 2024
Project Advertised for Bids
January 2024
Design Begins
2023
Reconstruction maintained in updated CIP with planned construction in FY ’23-‘24
2021
Reconstruction identified as a need in updated Sewer Collection System Master Plan
2019
Reconstruction added to CIP with planned construction in FY ’21-‘22
1981
Lift #4 Constructed
LAST UPDATED: 04/22/26