CAPITAL INVESTMENTS | Wastewater

Lift Station No. 4 Reconstruction

Lift Station No. 4.

DESCRIPTION

PROJECT ID: S 11.0
ESTIMATED COST: $600,000
ACTUAL COST: TBD
  • Includes well structure, pumps, ventilation system, internal piping, and electrical control system upgrades
  • Design will need to be analyzed during design and may require additional property for new pump chamber
  • Odor control system will need to be included

WHY IT’S NEEDED

Lift Station No. 4 was built in 1981 and the submersible duplex pump station has experienced corrosion on both metal and brick. Replacement of the wetwell will increase capacity, eliminate porous brick, and safeguard the environment. Ventilation of the structure is poor and electrical systems are nearing the end of their expected lives.

PROJECT STATUS:
In Progress
PROJECT MILESTONES

1981

Lift #4 Constructed

2019

Reconstruction added to CIP with planned construction in FY ’21-‘22

2021

Reconstruction identified as a need in updated Sewer Collection System Master Plan

2021

Reconstruction maintained in updated CIP with planned construction in FY ’22-‘23

2023

Reconstruction maintained in updated CIP with planned construction in FY ’23-‘24

January 2024

Design Begins

April 2024

Project Advertised for Bids

May 2024

Bids Opened

August 2024

Traffic Control Plan approved (see plan), construction slated to begin.

December 2024

All systems functional and operating, and streets re-opened. Project substantially complete and punchlist begins.

LAST UPDATED: 12/03/24

© Copyright - City of Hermiston