CAPITAL INVESTMENTS | Wastewater
Lift Station No. 4 Reconstruction
Lift Station No. 4.
DESCRIPTION
PROJECT ID: | S 11.0 |
ESTIMATED COST: | $600,000 |
ACTUAL COST: | TBD |
- Includes well structure, pumps, ventilation system, internal piping, and electrical control system upgrades
- Design will need to be analyzed during design and may require additional property for new pump chamber
- Odor control system will need to be included
WHY IT’S NEEDED
Lift Station No. 4 was built in 1981 and the submersible duplex pump station has experienced corrosion on both metal and brick. Replacement of the wetwell will increase capacity, eliminate porous brick, and safeguard the environment. Ventilation of the structure is poor and electrical systems are nearing the end of their expected lives.
PROJECT STATUS:
In Progress
PROJECT MILESTONES
1981
Lift #4 Constructed
2019
Reconstruction added to CIP with planned construction in FY ’21-‘22
2021
Reconstruction identified as a need in updated Sewer Collection System Master Plan
2021
Reconstruction maintained in updated CIP with planned construction in FY ’22-‘23
2023
Reconstruction maintained in updated CIP with planned construction in FY ’23-‘24
January 2024
Design Begins
April 2024
Project Advertised for Bids
May 2024
Bids Opened
August 2024
Traffic Control Plan approved (see plan), construction slated to begin.
December 2024
All systems functional and operating, and streets re-opened. Project substantially complete and punchlist begins.
LAST UPDATED: 12/03/24