CAPITAL INVESTMENTS | Wastewater

Lift Station No. 4 Reconstruction

Lift Station No. 4.

DESCRIPTION

PROJECT ID: S 11.0
ESTIMATED COST: $600,000
ACTUAL COST: $858,527.37*
  • Includes well structure, pumps, ventilation system, internal piping, and electrical control system upgrades
  • Design will need to be analyzed during design and may require additional property for new pump chamber
  • Odor control system will need to be included

* Actual cost affected by inflation on electrical and control components and expansion for street resurfacing and reconstruction from the original project scope.

WHY IT’S NEEDED

Lift Station No. 4 was built in 1981 and the submersible duplex pump station has experienced corrosion on both metal and brick. Replacement of the wetwell will increase capacity, eliminate porous brick, and safeguard the environment. Ventilation of the structure is poor and electrical systems are nearing the end of their expected lives.

PROJECT STATUS:
Complete
PROJECT MILESTONES

December 2024

All systems functional and operating, and streets re-opened. Project substantially complete and punchlist begins.

August 2024

Traffic Control Plan approved (see plan), construction slated to begin.

May 2024

Bids Opened

April 2024

Project Advertised for Bids

January 2024

Design Begins

2023

Reconstruction maintained in updated CIP with planned construction in FY ’23-‘24

2021

Reconstruction identified as a need in updated Sewer Collection System Master Plan

2019

Reconstruction added to CIP with planned construction in FY ’21-‘22

1981

Lift #4 Constructed