PROJECT ID: | S 13.0 |
ESTIMATED COST: | $600,000 |
ACTUAL COST: | $612,737* |
- Includes a well structure, pumps, internal piping and electrical and control system upgrades
- Additional property may be needed to accommodate construction and increased wetwell size
- Odor control system will be included
- Design will include evaluation of extending gravity sewer line to Lift Station No. 3 under Highway 395. May be more cost effective than replacing both lift stations independently.
*Savings of nearly $80,000 by delaying paving and sidewalk development as part of upcoming N. 1st Place Road Improvement Project.
WHY IT’S NEEDED
Lift Station No. 6 was built in 1981 and the submersible duplex pump station has experienced corrosion on metal and concrete. The existing structure is 22 feet deep and receives all discharges from the community pool, and the wetwell’s capacity is insufficient to accommodate sewage flows without excessive pump cycles. A larger wetwell will provide more time between pump cycles, simultaneously providing a buffer against overflows and system backups.
PROJECT STATUS:
Complete
PROJECT MILESTONES
July 2021
Design begins in conjunction with design work for N. 1st Place roadway improvements.
March 2022
Project advertised for bids.
April 2022
Four responsive bids received. Contract awarded to C & E Trenching for $689,179. (Staff report)
August 2022
Contractor begins work in conjunction with decommissioning Lift 3.
September 2022
Contractor delayed to accommodate boring work for Lift 3.
November 2022
Work resumes.
December 2022
Underground work is complete.
January 2023
Project complete. North 1st Place reopened to traffic after temporary surface restoration installed.
LAST UPDATED: 02/16/23