Lift Station No. 7 Reconstruction

Lift Station No. 7.

DESCRIPTION

PROJECT ID: S 16.0
ESTIMATED COST: $610,000
ACTUAL COST: TBD
  • Installs duplex pumps and upgraded electrical and control systems
  • Replaces existing mechanical pumps, rails, and valves
  • Replaces roof structure with a lid integrated into the sidewalk
  • Wetwell storage capacity may need to be increased based on growth predictions

WHY IT’S NEEDED

The pump station was built in approximately 1981. The existing duplex pumps and electrical systems need to be replaced.

PROJECT STATUS:
Planned
PROJECT MILESTONES

Schedule for 2023-24

LAST UPDATED: 01/18/23