CAPITAL INVESTMENTS | STREETS
N.W. 2nd Street Paving
N.W. 2nd Street.
DESCRIPTION
PROJECT ID: | ST 13.0 |
ESTIMATED COST: | $770,000* |
ACTUAL COST: | TBD |
- Paves about 500 feet of N.W. 2nd Street from W. Elm to W. Cherry Avenue.
- Paves about 310 feet of W. Dogwood from N.W. 2nd Street to N.W. Spruce
- Includes grading, storm drainage, asphalt, centerline stripes, and crosswalk.
* May be funded by local improvement district
WHY IT’S NEEDED
The gravel roadway has no sidewalks and unrestricted access from parking and open areas. Improvements will minimize maintenance, allow for increased traffic, increase pedestrian safety, and ensure functional roadway for community and business development.
PROJECT STATUS:
In Progress
PROJECT MILESTONES
February 2025
City Council initiates formation of LID
April 2025
Preliminary Engineering Report Completed
September 2025
Council approves LID to pay for NW 2nd Street portion. Dogwood portion to be paid by City.
“Hermiston City Council Approves Step Toward Local Improvement District”
Fall 2025
Full design begins
LAST UPDATED: 09/26/25