CAPITAL INVESTMENTS | WATER

Well 6 Chlorination Structure

Current chlorination system structure for Well No. 6.

DESCRIPTION

PROJECT ID: W 9.0
ESTIMATED COST: $450,000
ACTUAL COST: TBD
  • Block structure building is about 10 feet by 30 feet, to be verified during design
  • Ventilation system and chlorination system
  • Chlorine scales
  • Chlorine emergency alarms
  • Safety equipment

WHY IT’S NEEDED

The chlorine room at Well No. 6 is 5 feet by 8 feet and too small for its current use, and is constructed of fiberglass. It was originally constructed to occasionally store chlorination equipment. It is now in constant use and has been damaged during the exchange of chlorine cylinders.

A larger building will allow more efficient operation of the well.

PROJECT STATUS:
In Progress
PROJECT MILESTONES

2023

Design work has begun.

LAST UPDATED: 08/23/23