CAPITAL INVESTMENTS | WATER

Well No. 5 Water System Improvements

DESCRIPTION

PROJECT ID: W 30.0
ESTIMATED COST: $520,000
ACTUAL COST: $1,032,867.68*
  • Installs a new deep well pump
  • Replaces three booster pump motors
  • Improves electrical components and controls, including variable frequency drives

* Cost increase came from adding approximately 1,000 feet of new pipe from Well #5 to the north at the intersection of Geer & Theater, adding efficiency as work was already taking place nearby.  This additional main increases redundancy and capacity to serve areas north of Theater Lane. Additionally, significant inflation occurred between preliminary design and when bids were received.

WHY IT’S NEEDED

Well No. 5 has become the city’s primary water source in recent years and provides water to the main pressure zone, which is the baseline for the entire water system. However, the current pumping capacity is less than the water right associated with it. The project will increase pumping capacity to allow the city to use its full water right of 5,000 gallons per minute.

PROJECT STATUS:
Complete
PROJECT MILESTONES

May 2024

Project complete

Winter 2023-24

Well testing and punchlist items.

November 2023 

Work substantially complete.

September 2023

Work resumes

May 2023

Piping work complete with planned work stoppage to avoid interrupting Well #5 production during peak irrigation season.

March 2023

Piping work begins

January 2023

Project Awarded to R&G

December 2022

Five bids opened, with R&G Excavating the low bid at $756,880; well over the engineer’s estimate of $550,000.

November 2022

Project Advertised

July 2022

Design Begins

LAST UPDATED: 04/22/26